Tips: Underground Conduit Placement 👷

Some of our Race customers require Underground Conduit Placement in order to run fiber-optic to the home.  We at Race want to ensure that our customers have the information they need to make this a smooth process and have provided the following specifications to help.  The homeowner/developer/contractor is responsible for providing and adhering to the following underground requirements set by Race.

Remember that you can always call us at 877-722-3833 for any assistance.       

Scheduling ⏰

  • RACE needs to submit permit to Pole Owner and permit approved before any of these specifications can be executed.
  • Prior to the installation of any conduit, a RACE Communications Field Engineer will need to be scheduled to verify conduit route, pole conduit stub out, and home stub out.
  • A RACE Communications Field Engineer will need to be scheduled for conduit inspection before trench fill. Two days advance notice must be provided prior to conduit inspection, with a three day inspection window.
  • It is the homeowner / developer / contractor’s responsibility to contact “Call Before You Dig” prior to any excavation. 
  • It is the homeowner / developer / contractor’s responsibility to contact local building department for any permitting requirements.
  • RACE Communications will reserve the right to refuse fiber installation if any of these specifications are not met.
  • A scaled print of the project showing the lot layout. To be reviewed with RACE Communications Field Engineer.

Dimension 📐

  • Any conduit run under 250’ will require 3/4 inch Schedule 40 PVC conduit.*
  • For any run between 251’ and 400’, it will require a 3/4 inch Schedule 40 PVC conduit with a pull box.*
  • Any conduit run over 400’ will require a pull box location.
  • All conduits, sweeps, and couplers will be glued with PVC cement.
  • Sweeps are to be utilized at any splice location, riser pole, or structure. No Hard 90 degree bends to be used. A maximum of 3 sweeps in conduit run. 
  • All conduit runs to have ¼” nylon pull rope installed within it. Both ends of rope should be secured to outside of conduit and accessible.
  • Conduit at pole location will need to be stubbed up 2’ minimum.
  • Conduit at structure location will need to be stubbed up 4’ minimum.
  • Conduit install depth on private property is 12 – 18 inches. Please contact local building department for required private property depth based on county specifications. 
  • *note: you will not be able to run additional wires or cables in the same conduit should you use a 3/4 inch conduit. Underground Conduit Placement Specifications

One thought on “Tips: Underground Conduit Placement 👷

  1. It’s good to learn that all conduits underground should be glued with PVC cement. My brother is wanting to start working construction and he was wondering how he could work correctly with conduits underground. I’ll be sure to tell him to glue the conduits to PVC cement.

    Like

Leave a Reply to Aaron White Cancel reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s